Hire of work in Thailand is a contract in which one party, the contractor, agrees to complete a defined piece of work for another party, the employer, who agrees to pay remuneration for the finished result. The rules sit in Sections 587 to 607 of the Thai Civil and Commercial Code. They govern construction contracts, fit-out works, machinery installation and any other engagement paid for a result rather than for time.
Related: a hirer is not liable for the contractor’s harm to third parties except under Section 428. See our note on tort liability in Thailand.
For employment contracts under Sections 575 to 586 of the Civil and Commercial Code, see our guide to hire of services in Thailand.
Where a contractor or service provider simply holds the client’s property for safekeeping, the Code’s rules on the deposit contract in Thailand apply instead.
The employer pays for the result, and payment falls due on delivery of the work unless the contract sets staged payments (Sections 587 and 602). The employer may end the contract early for serious delay (Section 593), demand that defects be cured and bring in a third party at the contractor’s cost (Section 594), and withhold payment for late or defective work unless the contractor gives proper security (Section 599). Unless the contract says otherwise, defects liability runs for one year from delivery, or five years for a structure on land other than a wooden building (Section 600). A claim for defects must be filed within one year from the day the defect appears (Section 601).
What Is Hire of Work in Thailand?
Hire of work in Thailand (จ้างทำของ) is defined in Section 587 of the Civil and Commercial Code. The contractor undertakes to complete a particular work for the employer, and the employer undertakes to pay remuneration for the result of that work. The defining feature is the result: the contractor is paid to deliver a finished outcome.
That focus on the result separates hire of work from hire of services, which the Code treats in a separate chapter. Hire of services pays for work performed; hire of work pays for a finished result, and the contractor carries the risk of reaching it.
Most construction and engineering engagements fall within this chapter. A main contract to build a factory, a fit-out of leased office space, the installation of a production line and the renovation of a villa are all contracts for a result. Where a contractor stops work halfway, our guide on a contractor who abandons a villa project in Thailand covers the steps an owner should take on site.
What Must the Contractor Do While the Work Is in Progress?
The Code places three duties on the contractor during the works. The contractor must let the employer inspect the work, must warn the employer about unsuitable materials or wrong instructions, and remains answerable for any subcontractor it brings in. Each duty gives the employer a point of control before handover.
Section 592 requires the contractor to allow the employer, or the employer’s agent, to inspect the work at any time while it is being carried out. An employer can therefore appoint an engineer or project manager to visit the site and check progress against the drawings.
Section 591 protects the contractor where a defect or delay comes from materials the employer supplied or from the employer’s own instructions. The contractor is not liable in that case. The protection falls away if the contractor knew the materials or instructions were unsuitable and failed to tell the employer.
Section 607 allows the contractor to subcontract all or part of the work. The exception is a contract whose essence lies in the contractor’s own knowledge and ability. Even where subcontracting is allowed, the contractor stays liable for the conduct and any fault of the subcontractor.
When Can the Employer End Hire of Work in Thailand for Delay?
Section 593 lets the employer terminate before the delivery date in three situations: the contractor fails to begin the work in due time, the contractor delays in breach of the contract, or the contractor delays without fault on the employer’s side so that completion within the agreed time can be foreseen as impossible. The employer need not wait for the deadline to pass.
Late delivery itself is covered by Section 596. If the contractor delivers after the date fixed in the contract, or after a reasonable time where no date was fixed, the employer may reduce the remuneration. Where time is of the essence of the contract, the employer may instead terminate it.
The employer must act at the right moment. Section 597 provides that if the employer accepts delivery of the work without reservation, the contractor is not liable for the delay. An employer who intends to claim for late completion should record that reservation in writing at handover. Where the contract fixes a daily sum for delay, our guide to liquidated damages in Thailand explains how the Code treats that agreed amount.
What Can the Employer Do About Defective Work?
The employer has two tools against defective work. Before completion, Section 594 allows the employer to require the contractor to cure the defect within a reasonable time and, failing that, to hand the work to a third party at the contractor’s risk and expense. After delivery, Section 599 allows the employer to withhold payment until the position is resolved.
Section 594 applies when it can be foreseen with certainty during the works that the result will be defective, or will breach the contract, because of the contractor’s fault. The employer gives notice requiring the contractor to cure the defect or perform as agreed within a reasonable time stated in the notice. If that time passes, the employer may have a third party repair or continue the work. The contractor bears the risk of loss and all the expenses.
Section 599 covers delivery that is late or defective. In either case the employer may retain the remuneration, unless the contractor provides proper security. This right of retention is the employer’s main lever once the work has been handed over.
Does Accepting the Work Waive Defect Claims?
It can. Under Section 598, if the employer accepts defective work without reservation, whether expressly or by conduct, the contractor is not liable. Two exceptions apply: a defect that could not have been discovered at the time of acceptance, and a defect the contractor concealed. A handover certificate should therefore list known defects and reserve the employer’s rights.
How Long Is the Defects Liability Period Under Hire of Work in Thailand?
Section 600 sets the default period. Unless the contract provides otherwise, the contractor is liable only for defects that appear within one year from delivery. For a structure on land, other than a building made of wood, the period is five years. The limit does not apply where the contractor concealed the defect.
| Rule | Period or effect | Source |
|---|---|---|
| Defects in work in general | Contractor liable for defects appearing within one year from delivery | Section 600 |
| Structure on land (not a wooden building) | Contractor liable for defects appearing within five years from delivery | Section 600 |
| Defect concealed by the contractor | The one-year and five-year limits do not apply | Section 600 |
| Different contractual period | The contract may provide otherwise | Section 600 |
| Time to sue the contractor | No action after one year from the day the defect appeared | Section 601 |
The two periods work together. Section 600 decides which defects the contractor answers for. Section 601 then sets a separate deadline for suing: one year counted from the day the defect appeared. A crack that appears in the fourth year of a concrete building falls within the five-year liability period, but the claim on it must be filed within one year from the day it appeared.
When Is Payment Due Under Hire of Work in Thailand?
Section 602 states that remuneration is payable when the employer takes delivery of the work. If the work is to be delivered in parts and the remuneration is fixed for each part, the remuneration for each part is payable when that part is received. The Code therefore links payment to delivery, not to the passage of time.
A construction contract may replace this default with milestone or progress payments, and Section 602 itself contemplates delivery in parts. Where the contract is silent, the contractor cannot demand the full price before handover, and the employer cannot hold back the price after accepting a complete and defect-free result.
Who Bears the Loss if the Work Is Destroyed Before Delivery?
The answer depends on who supplied the materials. Under Section 603, if the contractor supplied them and the work collapses or is damaged before proper delivery, the contractor bears the loss, unless the employer caused it. Under Section 604, if the employer supplied the materials, the loss falls on the employer, unless the contractor caused it.
In both cases remuneration is affected. Where the contractor supplied the materials, no remuneration is payable for work destroyed before delivery. Where the employer supplied them, Section 604 also provides that no remuneration is payable, unless the employer caused the loss. Insurance and risk clauses in a construction contract should be read against these two default rules.
Can the Employer Terminate Without Cause?
Yes. Section 605 allows the employer to terminate the contract at any time while the work is unfinished, provided the employer pays the contractor compensation for any damage arising from the termination. No breach by the contractor is needed.
The cost of using this right is the contractor’s loss. Sections 593 and 594 do not contain the compensation condition found in Section 605. An employer with a ground under one of those sections should say so in the termination notice and state which section it relies on.
Points to Settle in a Hire of Work Contract
The Code supplies default rules, but several of them can be adjusted by agreement. Section 600 expressly yields to the contract, and Section 602 allows staged payment. The points below follow directly from the sections above.
- Scope and result. Describe the finished result in drawings and specifications, since the contractor is paid for that result under Section 587.
- Materials. State who supplies which materials. That choice decides the risk of loss before delivery under Sections 603 and 604, and the contractor’s defence under Section 591.
- Time. Fix a completion date and say whether time is of the essence, which opens termination under Section 596.
- Handover. Provide for a written handover record that lists defects and reserves claims, to avoid the effect of Sections 597 and 598.
- Payment and retention. Set milestones under Section 602 and the security the contractor must give to release retained sums under Section 599.
- Defects period. Decide whether to keep the Section 600 periods or agree a different period, and diarise the one-year filing deadline in Section 601.
- Subcontracting. Say whether subcontracting needs consent, bearing in mind that the contractor stays liable for subcontractors under Section 607.
Our contract lawyers in Thailand review construction and works contracts against these Civil and Commercial Code rules.
Hire of Work in Thailand: Questions and Answers
Is a construction contract a hire of work contract in Thailand?
How long is a contractor liable for defects in a building?
What is the deadline to sue a contractor for defects?
Can an employer withhold payment from a contractor?
Can an employer cancel a hire of work contract before completion?
Conclusion
Hire of work in Thailand rests on a simple bargain: the contractor delivers a result and the employer pays on delivery. Around that bargain the Code sets firm rules on delay, defects, risk and termination. The employer’s position depends on acting at the right time: reserving claims at handover, retaining payment while defects remain, and filing within one year from the day a defect appears. For a project already in difficulty, see our guide on a contractor who abandons a villa project. The Thai text of the Civil and Commercial Code is published by the Office of the Council of State, and amendments appear in the Royal Thai Government Gazette.